Global planning
For this project I made a global planning I can consult to see if I'm on the right track. I have 11 days to complete this project. The deadline is June 30 at 12:00 PM. I've devided my project into three stages. The first stage is pre-production, the second stage is production and the final stage is polishing. Day 01 - June 20 - Pre-production Day 02 - June 21 - Pre-p roduction Day 03 - June 22 - Production Day 04 - June 23 - Production Day 05 - June 24 - Production Day 06 - June 25 - Production Day 07 - June 26 - Production Day 08 - June 27 - Production Day 09 - June 28 - Production Day 10 - June 29 - Polishing Day 11 - June 30 - Polishing I've devided my project into three stages. The first stage is pre-production, the second stage is production and the final stage is polishing. Pre-production tasks project set up game architecture planning set up class structure fo...